The Precinct: Project Status Update
The City of Victor Harbor has provided a detailed update on the Regional Community, Sport and Recreation Precinct (the Precinct), outlining where the project is up to and the key decisions ahead.
City of Victor Harbor Chief Executive Officer, Chris White, briefed Elected Members in front of a full gallery at the Civic Centre on Monday, 16 November 2026, covering the project's status, costs and the options before Council.
"Since joining Council, I've heard from many people in our community about the Precinct, and it's clear that a detailed update would help to create a consistent understanding of the project status," Mr White said.
"This briefing was about giving Elected Members and our community a clear and honest picture of the project as it stands today."
The Precinct, proposed for Lot 202 Armstrong Road, would include four multipurpose indoor courts, a gymnastics facility, a gym, community and meeting spaces, change facilities and more than 160 car parks. Childcare, allied health and food and beverage offerings would also form part of the site.
As well as basketball and gymnastics, the facility has the potential host fitness classes, dance, events, meetings and inclusive programs for people of all ages.
"I don't think many people would argue our community would be worse off for having a facility like this," Mr White said.
"The question for Council is whether the benefits justify the costs and risks, and how best to deliver it."
Development approval and detailed design for the Precinct are complete, with Building Rules approval still to come. If approvals and Council decisions are in place, construction could begin as early as 1 March 2027, with the recreation facility targeted for completion by May 2028.
Two matters need to be resolved before the project can proceed. The first is a decision by the Minister for Local Government on Council's community land revocation application. The second is grant funding, with $3.33 million secured towards Council's minimum requirement of $4 million, leaving a gap of around $669,000. Further grant applications are underway.
The current Heads of Agreement with Council's delivery partner, Accord Property, expires on 31 December 2026. If these conditions are not met by then, Council will need to decide whether to extend the agreement or consider other options.
Under the proposed partnership model, Council would retain ownership of the land and lease it to the delivery partner. Council's capital contribution is $15.7 million, including at least $4 million in grant funding, with the private partner contributing around $10 million for the recreation facility.
"The partnership is structured around $10 million in private investment, and a target of $4 million in additional funding from State and Federal governments, to deliver a facility our community needs, with the commercial uses on the site intending to help offset costs," Mr White said.
"A comparable four-court facility built by Council alone, with a typical $7.5 million in grant support, could require an estimated $18.5 million of Council funding, which would be very difficult to manage under Council’s current financial position."
Under the current proposal Council's ongoing operating contribution is estimated at around $1.2 million a year. There are as-yet-unresolved elements of the operating model, most significantly concerning the potential need for a subsidy of around $290,000 a year to support gymnastics. A component of this $1.2 million estimate includes a contingency to support this potential subsidy in part, but discussions with the proposed operator and local gymnastics stakeholders are ongoing, and an adjustment upwards or downwards is possible depending on how these discussions are resolved. Once an in-principle position has been settled, the matter will be reported to Council with options on a pathway forward, with full costings included.
In terms of impact on ratepayers, Council's Long Term Financial Plan includes a 5.2% additional rate increase to support the project, which is less than the 5.5% the community was consulted on. The increases will be spread over multiple years to reduce impact, with 2.2% already applied, and the remaining 3% intended to be raised in 2027/28 (1.5%) and 2028/29 (1.5%).
Proposed protections for the community include user fees for the recreation facility capped at no more than 5% above comparable regional facilities, an advisory group involving regular users, buyback rights for Council, and a share of profits achieved above agreed levels.
To date, Council has spent $592,231 (excluding GST) to progress the Precinct, mainly on feasibility, design, planning and community engagement.
Council will consider an update to its Long Term Financial Plan at its meeting on 24 November 2026. A decision on the next stage of the project is expected at the December Council meeting or a special meeting before the Heads of Agreement expires.
"This is a decision for Council," Mr White said. "My role is to make sure Elected Members and our community have the information they need."
The presentation slides from the briefing are available in 'Project Updates' at victor.sa.gov.au/theprecinct