Yandra Terrace Stormwater Outlet Replacement

Repairing and future-proofing our stormwater infrastructure.

Storm events in 2022 significantly damaged the Yandra Terrace stormwater outlet in Hayborough. The area surrounding the outlet faced substantial erosion, culminating in the collapse of a retaining wall and the undermining of the stormwater outlet pipe.

While the City of Victor Harbor undertook emergency works to backfill erosion and install temporary safeguards following storms, a more permanent solution was required to future-proof the stormwater infrastructure.

Emergency works at Yandra Terrace in 2022 Emergency works at Yandra Terrace

Images: Emergency works undertaken by the City of Victor Harbor following storm events.

What did this project involve?

This project aimed to repair and improve the Yandra Terrace stormwater outlet, providing a sustainable infrastructure solution that can better withstand increasingly severe storms along our coastline.

Works involved with this project included:

  • Removal of existing pipe and pit structures
  • Installation of new stormwater outlet
  • Installation of new sandbag coastal protection wall
  • Revegetation of reinstated sand dunes area
  • Removal and reinstatement of railway.

Works to replace the stormwater outlet were complex due to the site being positioned within a vulnerable dune system, beneath the SteamRanger railway and at a high energy point of the coast.

In consultation with Council, the contractor engaged to undertake this project identified and protected areas of dune vegetation that should not be disturbed, and an independent geotechnical consultant provided advice throughout the project.

The City of Victor Harbor worked closely with SteamRanger on this project.

Yandra Terrace Stormwater Outlet in April 2023 Yandra Terrace Stormwater Outlet April 2023

Images: Yandra Terrace stormwater outlet in April 2023.

New stormwater outlet pipe New stormwater outlet - aerial image

Images: Completed new stormwater outlet in October 2023.

Timeline

Works to prepare the site for construction, including upgrading access tracks for construction vehicles and flagging off vegetation areas, took place in early 2023. Major construction works occured throughout September and early October 2023.

The SteamRanger railway was temporarily closed in late September to facilitate works, but has since been re-opened.

Ongoing work is still being undertaken to ensure revegetation and rehabilitation of the sand dunes area.

Funding

The Yandra Terrace stormwater outlet replacement was supported by grant funding from the Stormwater Management Authority.

More Information

For further information about this project, contact the City of Victor Harbor on (08) 8551 0500 or email localgov@victor.sa.gov.au.